Tower Project Update

Tower Project Update

Heritage Lottery Fund has offered St Thomas Beckett church a grant of £181,300 under its Grants for Places of Worship scheme to carry out urgent tower repair works, the installation of mains water and drainage a WC and for heritage activities.

Statement of funds (rounded)

£181, 000 – HLF

£8,500 – Parochial Church Council

£4,500 – from fundraising activities

£5,500 –pledged from Church and community fundraising

£199,000 total so far

Our target estimate will be confirmed in March’s Tower Project update.

From where will additional funds come?

Other grants

Local fundraising activities

Sponsored events

Donations & legacies

Progress on building works

Our first task in November was to advertise and select a new conservation architect to take this project to the next stage. Carl Andrews from Soul Architects was appointed to commence work at the beginning of January. Check out Carl and the rest of our team on the Church website http://tugby.org.uk/team

Carl is already busy scoping and organising for investigative works to the tower. Plans for building works will be drawn up between May and July and a proposal submitted to Heritage Lottery Fund for approval.

How can you help?

We would really like people to get involved in drawing up exciting and innovative plans to celebrate Tugby’s heritage. Several ideas have already been suggested:

Anglo-Saxon Encampment, eating, drinking, making merry the medieval way

Family Heritage Treasure Hunts,

Church Guided Tours, or offer to lead them

Medieval Craft Activities,

Bat Watching for Kids,

Annual lectures taking in subjects such as medieval archaeology

Try you hands at bell ringing

Organise a fundraising event

Take up training (free) to help manage our website

Can you think of any more?

Contact any of the project team through the website http://tugby.org.uk/team

Facebook Tugby Together

Tweet to @tugbytogether

Our key milestones

November 2015 – Receive Heritage Lottery Fund grant and go-ahead 2015

January 2016 – Appoint Conservation Architect

February – appoint a contractor for roof investigations

March – Undertake roof opening up works

April/May – Prepare detailed drawings & advertise for main contractor

June – Submit plans to HLF & Historic England

July – Issue tenders for reordering & submit applications for statutory permissions

August – Tender reviews & Submit plans to HLF

Autumn/Winter – Celebrating success with our Heritage Festival Day

March 2017 commence works

Autumn 2017 Celebrating our built heritage – summer 2017

 

Related Blogs

Posted by Sally Webb | July 10, 2017
Hats off for an excellent hard hat tower tour! (Published belatedly)
Here's one group of intrepid explorers happily peering over during their ascent to the top of the tower.  Geoff Beetham of Stone Edge conducted tours of the tower, while Carl Andrews...
Posted by Sally Webb | February 13, 2017
Calling All Bell Ringers!
Alan Rees writes: The call went out - Tugby church needs more bell ringers! The call was answered; In December half a dozen or so villagers met in the belfry...
Posted by Sally Webb | January 11, 2017
Ancient church tower in East Leicestershire secures significant Heritage Lottery Fund investment for urgent repairs.
The Heritage Lottery Fund (HLF) has awarded St Thomas Beckett Church, Tugby, £154,100, for urgent repairs to the tower roof and internal structures. Specifications for the grant award include improved...